Old Narrandera Road Upgrade

construction

Council is upgrading a section of Pine Gully Road and Old Narrandera Road to improve safety and traffic flow.

Project Updates

11 Oct 2023

Upgrade nearing completion

The Old Narrandera Road upgrade project is entering its final phase.

Old Narrandera Road reopened to through traffic earlier this week. While the road is open, the remaining works being carried out under traffic control including a reduced speed limit of 40 kilometres per hour.

Contractors are currently completing work on the road base, which will provide a solid foundation for the road surface.

Weather permitting, it is expected the final bitumen seal will be applied early next week.

Once the final seal has been applied, contractors will move onto the finishing touches, which will include installing guard rails and signage and undertaking line marking.

Receive email updates about Old Narrandera Road

Project Information

This upgrade forms part of Pine Gully Road Corridor Works servicing the residents of Gobbagombalin, Estella and Charles Sturt University.

This project will increase the capacity of these roads to accommodate both the present and future traffic demands in the area.

The upgrade includes:

  • reconstructing pavement of Old Narrandera Road from a point approximately 100m west of the Olympic Highway intersection to, and including, the Pine Gully Road intersection
  • widening this section of Old Narrandera Road from 2 to 4 lanes (2 lanes in each direction)
  • creating a dedicated right turn lane onto Pine Gully Road from Old Narrandera Road
  • creating a channelised T-intersection with a left turn slip lane out of Pine Gully Road onto Old Narrandera Road
  • reconstructing approximately 100m of Pine Gully Road pavement from the Old Narrandera Road intersection
  • improving drainage by replacing culverts and constructing table drains
  • installing new signage, concrete medians and guardrails.

The upgrade is expected to take approximately 12 weeks to complete (August to October 2023), weather depending.

Benefits of this project

This project will:

  • make your journey smoother by improving the condition of Old Narrandera Road between the Olympic Highway and Pine Gully Road
  • improve traffic flow in the area by doubling the number of lanes on this section of road from 2 to 4
  • improve traffic flow and safety with new dedicated right and left turning lanes for vehicles
  • improve safety with the installation of new guard rails, raised concrete medians, signage and line markings.

There will be some disruption for road users during this upgrade, with a temporary speed limit reduction, lane closures, and road closures with detours and traffic control in place at different stages of the project.

Keep up to date with traffic disruptions by:

  • checking the latest project update on this page
  • visiting Live Traffic NSW
  • subscribing to receive email updates (see the subscription form above).

This project is funded by Wagga Wagga City Council under the Pine Gully Road upgrade project.

Project Documents & Files

No documents or files were found.

Project Notifications

Project Images

Contact us

For further information about this project please contact our project team on 1300 292 442 or council@wagga.nsw.gov.au