75 percent of project now complete

Council contractors have achieved significant progress in recent months with the opening of the pump track, jump track and mountain bike loop.

Progress on the community building has seen the roof installed, services fit out complete, external brickwork and internal walls complete. Fittings, fixtures and finishes work is now underway.

Earthworks and pavement construction on the velodrome is finished, landscaping is nearing completion and signage has been installed in the learn-to-ride space.

Works are scheduled to finish at the end of this year, weather permitting.

Check out this bird’s-eye view of the new Multisport Cycling Complex taking shape at Pomingalarna Reserve: