Museum redevelopment update - 23 June

  • The roof has been completed and internal wall framing and ceiling grid has been installed.
  • Earthworks, inground services and bricklaying have been completed by contractors.
  • Cladding is completed on the main building, windows installed, and the electrical fit out completed.
  • Plastering is underway in the main building.
  • Additionally, the schoolhouse has been restored, painted and vinyl flooring installed. The schoolhouse will continue to be used as a classroom when the museum is re-opened.