- The roof has been completed and internal wall framing and ceiling grid has been installed.
- Earthworks, inground services and bricklaying have been completed by contractors.
- Cladding is completed on the main building, windows installed, and the electrical fit out completed.
- Plastering is underway in the main building.
- Additionally, the schoolhouse has been restored, painted and vinyl flooring installed. The schoolhouse will continue to be used as a classroom when the museum is re-opened.