Works to upgrade Dunns Road are scheduled to start by the end of January, subject to Council receiving stormwater pipes which have been held up due to Covid 19.
The work will be carried out on the three kilometre unsealed section of the road between 7am and 5pm weekdays and 8pm to 4pm Saturdays.
During the work, the road will be closed to traffic. Detours will be in place. Local residents within the unsealed section of the road will maintain access.
The sealing of the road is expected to be completed by July 2022.