Riverside Stage 2 transformation taking shape

Work on Stage 2 is progressing. The playground designed by Moduplay, is more than 85 per cent complete.

Concrete works for the shared path and pavement, along with the tiered seating works near the new kiosk are progressing, and the internal fit out is underway on the new amenities block.

The new main stage, which will cater for a wide range of events, is also taking shape with the structural steel frames installed and block work and slabs for the stage also in progress.

The project is expected to be completed by end of April 2022, weather permitting.